Wellcome to National Portal
Text size A A A
Color C C C C

সর্ব-শেষ হাল-নাগাদ: ১৯ নভেম্বর ২০২৪

মূল পরিসংখ্যান

Present Installed Generation Capacity (MW) as on 31st October 2024

 

Public Sector

 No of Power Plant

Installed Generation Capacity (MW) 

 BPDB

40

6,350

APSCL

5

1,394

EGCB

4

1032

NWPGCL

7

1,401

B-R Power gen

2

312

RPCL

3

182

CPGCBL

 

1

 

1150

Subtotal

62

11,821 (43%)

Joint Venture

 

 

BCPCL (JV of NWPGCL & CMC, China)

1

1,244

BCPCL (JV of BPDB & NTPC, India)

1

1,234

Subtotal

2

2,478 (9%)

Private Sector

 

 

IPPs

64

10,153

SIPPs (BPDB)

0

0

SIPPs (REB)

9

251

15 YR. Rental

 ০

3/5 YR. Rental

0

00

Rental(No Electricity No Payment)

6

381

Subtotal

79

10,785 (39%)

Power Import

 

 

Bheramara HVDC

 

1,000

Tripura

 

160

Jarkhondo (India), Adani Power

 

1,496

Subtotal

 

2,656 (9%)

                        TOTAL

143

27,740*

 

*Including Captive Power, off grid Renewable Energy & Off grid HFO Total Installed Capacity (27,740+2,800+549+5) =31,094 MW

MAXIMUM DEMAND SERVED

16,477MW

30-04-2024

TRANSMISSION LINES (400 kV) 2,469Ckt. K.M FY-2024

TRANSMISSION LINES (230 kV)

4,250Ckt. K.M

FY-2024

TRANSMISSION LINES (132 kV)

8,845Ckt. K.M

FY-2024

GRID SUB-STATION CAPACITY (400/230 kV) 10,255 MVA  FY-2024
GRID SUB-STATION CAPACITY (400/132 kV) 3,315 MVA FY-2024

GRID SUB-STATION CAPACITY (230/132 kV)

16,975 MVA

 FY-2024

GRID SUB-STATION CAPACITY (230/33 kV)

4,80 MVA

 FY-2024

GRID SUB-STATION CAPACITY (132/33 kV)

  33,245 MVA

FY-2024

DISTRIBUTION LINES (33 KV & BELOW) (only BPDB)

51,419 K.M

FY-2024

CONSUMER NUMBER (BPDB)

43,03,324

FY-2024

 

 

 

 PRIMARY GRID SYSTEM OF BANGLADESH

 (As on June, 2024)

 (Click here for download Grid Map as pdf format.)